Question QB1: What was the project time frame for the implementation of X guidelines?
Answer Options:
- Less than 3 months
- 3-6 months
- 6-9 months
- 9 months to a year
- a year or longer
Format: Single select
Scale or Measurement: Count
Status: In review
Audience: TBD
Notes:
Question QB2a: Was the implementation project:
Answer Options:
- Completed
- Abandoned
- Postponed
Format: Single select
Scale or Measurement: Count
Status: In review
Audience: TBD
Notes:
Question QB2b: If completed, the amount of time to complete the project was:
Answer Options:
- Shorter than planned
- As planned
- Longer than planned
Format: Single select
Scale or Measurement: Count
Status: In review
Audience: TBD
Notes:
Question QB3: To what extent do you agree with the following statements?
Answer Options:
1) The project schedule was realistic.
2) Strategies to keep the project on schedule were effective.
Format: Item ranking (strongly disagree to strongly agree)
Scale or Measurement: Likert
Status: In review
Audience: TBD
Notes:
Introduction: From your perspective:
Question QB4a: What helped the project remain on schedule?
Answer Options: Open text
Question QB4b: What prevented the project from remaining on schedule?
Answer Options: Open text
Question QB4c: What strategies were used to help the project stay on schedule?
Answer Options: Open text
Question QB4d: What staff roles were required or used to design and execute the implementation?
Answer Options: Open text (also consider drop downs for selected roles)
Question QB4e: What staff roles were affected by the implementation?
Answer Options: Open text (also consider drop downs for selected roles)
Format: Multiple line response
Scale or Measurement: Qualitative word coding
Status: In review
Audience: TBD
Notes: